November 5, 2026
From the paved loop on the dam side of Lafayette Reservoir, the tower still stands in the water, wrapped in scaffolding. Since late summer it has been about 40 feet shorter. Crews used cranes and a barge to lift off the roof and the old operating house. Then they saw-cut concrete rings, each about three feet tall, off the stem, as Lamorinda Weekly reported in August. The paper called the structure "the symbol of the city."
The tower that came down was not the size anyone originally planned. The schedule for the new one is set by birds, frogs and the reservoir's wildlife season as much as by a construction crew. That is why the tower can look close to finished this winter while the full project runs until fall 2027.
Work on the dam and tower began in 1927. According to the East Bay Municipal Utility District's project page, the original plan called for a dam 33 feet taller than the one in place today, which would have created a reservoir nearly three times larger. The dam is earth-filled, built up from layers of compacted soil. During construction the soil could not support the planned height and the embankment began to move, so the dam was lowered. By then the outlet tower had already been built for the larger dam.
EBMUD puts it plainly: the tower, finished in 1929, is "40 feet too high due to a change in the dam height during construction." That means the outline Lafayette has known for nearly a century was left over from a bigger reservoir that was never built.
The extra height mattered once the state reviewed it closely. The tower is also the dam's spillway. After 2017, the California Division of Safety of Dams, known as DSOD, stepped up its statewide reviews. Seismic studies showed the tower could bend and break in a large earthquake. DSOD required EBMUD to strengthen the tower and the conduits under the dam and to add an onshore valve system for faster emergency response. The approved fix brings the tower down to match the dam it actually serves. The $14 million project is paid for by EBMUD ratepayers, and the reservoir does not need to be drained.
Since 2015, EBMUD has met with the Lafayette City Council seven times about the tower. In 2017 it presented three design options to the council, two of which would have kept the tower at full height. The shortened design was described as the most direct way to address the seismic risk. Then-Mayor Anderson favored it and suggested lightweight design elements to keep the tower's familiar look.
In 2023 the City formed a Citizen's Advisory Committee, and EBMUD held the project for more than a year while its engineers reviewed the committee's tower concepts. EBMUD says those concepts did not meet DSOD requirements. Lamorinda Weekly reported that residents raised objections at public meetings over the years and suggested other retrofit designs, none of which EBMUD found workable.
The final design keeps the tower's character in one key way. The top will carry a new metal operating house that EBMUD says "closely resembles the existing 100-year-old design." EBMUD's renderings label it a "Gazebo" and show the shorter tower at high, average and low water levels. The silhouette will be lower but recognizably the same shape.
The Lafayette Chamber of Commerce's August stakeholder update said the shortening began in early July with removal of the old operating house and then 13 concrete rings from the stem, and was on track to reach the new height by August 21. Before the new house can go on, crews have to build new corbels, the supports at the top of the shortened tower, and pour a floor inside it. In September, DSOD inspectors visited the site and reviewed the reinforcing steel and forms for those concrete corbels. EBMUD's September monthly report to its board says no significant concerns were noted.
The reservoir's wildlife sets the other limit. Because the work is close to water and streamside habitat, EBMUD obtained a permit from the California Department of Fish and Wildlife. A biological monitor is on site every workday from May through October, Lamorinda Weekly reported. The monitoring covers nesting birds, bats, bumblebees, the California red-legged frog, Alameda whipsnake, California tiger salamander, western pond turtle and San Francisco dusky-footed woodrat. Crews put netting on the tower to keep birds from nesting and worked with the biologist on a plan to move woodrat nests out of the work area.
When the seasonal environmental work window closes this fall, crews will stop work on the tower components. They are due back in spring 2027 to install new underwater slide gates and electric motors to operate them. That gap explains the timeline. The visible work on top can be done this year, and the tower still won't be back in full service for about another year.
| Phase | Timing on the schedule |
|---|---|
| Tower shortening | Started early July 2026, new height targeted for August 21 |
| Corbels and floor | Reinforcement and forms inspected by DSOD in September 2026 |
| New metal operating house | Installation scheduled by November 2026 |
| Seasonal pause | When the environmental work window closes, fall 2026 |
| Underwater slide gates and electric motors | Spring 2027 |
| Tower returns to full operation | Fall 2027 |
The tower pause starts as the fishing season picks up. EBMUD stocks the reservoir with trout from November through March, and it also holds catfish, bass and sunfish. Anglers need a California fishing license plus an EBMUD Fishing Access Permit from the Visitor Center. Under the 2026 Lafayette fee schedule, daily vehicle entry is $7, meters cost $1 per half hour, and daily fishing access is $6.
EBMUD's August update said fishing, hiking and picnicking stay open throughout construction. Here is how the work touches each part of the park:
Lamorinda Weekly reported that tower work happens on weekdays only, so weekends stay largely undisturbed at a park that draws more than a million visitors a year. Project trucks use only the stretch of Mt. Diablo Boulevard to and from the Acalanes Road ramp off Highway 24 and do not pass through downtown. EBMUD says the schedule may shift with weather and posts updates on its social channels and through construction alert subscriptions.
Two details from the planning stage are still open, and both concern what the old tower leaves behind. At a public meeting last February, people asked about the swallows that return to the tower every year. EBMUD said they will be able to come back once the work is done, according to Lamorinda Weekly. Crews come back in spring 2027 to install the underwater gates.
The concrete is the other detail. EBMUD has heard from community members who asked whether pieces of the original tower could be saved. In the August update, the agency said it was looking at ways to salvage material and planned to make "a historic token for the public." It said it would follow up once a formal plan is in place. Those rings were cut from the part of the tower built for a reservoir that never existed. Project updates are posted at ebmud.com/lafayettetower.
At Scott & Scott Real Estate Associates, we follow projects like this one because they shape everyday life in Lafayette. If you'd like to talk about what's changing around the reservoir, or about your own plans nearby, we would be glad to hear from you. Contact us for a personalized consultation.
Stay up to date on the latest real estate trends.
We understand that transitions are exciting, scary and stressful, but, more importantly, they are a huge step towards your future. Whether buying your first home or letting go of a lifetime of memories, the Scotts understand the process and will guide you through with timely information and sincere kindness.